Ticket #331 (closed planned_task: obsolete)

Opened 17 years ago

Last modified 15 years ago

BASE_PERSISTENCE_INTERMEDIATE_STORAGE_R0

Reported by: Astea Owned by: boyan
Priority: 3 Milestone: M03_PRE3
Component: BASE_PERSISTENCE Version: 2.0
Keywords: Cc:
Category: BASE Effort: 1
Importance: 20 Ticket_group: GROUP_PERSISTENCE_R0
Estimated Number of Hours: Add Hours to Ticket:
Billable?: Total Hours:
Analysis_owners: niki Design_owners: boyan
Imp._owners: Test_owners:
Analysis_reviewers: peko Changelog:
Design_reviewers: pav Imp._reviewers: meddle
Test_reviewers: Analysis_score: 3
Design_score: 3.5 Imp._score: 0
Test_score: 0

Description

Change History

comment:1 Changed 16 years ago by deyan

  • Category set to BASE
  • Design_score set to 0
  • Imp._score set to 0
  • Test_score set to 0
  • Analysis_score set to 0

Adding category

comment:2 Changed 16 years ago by peko

  • Importance changed from 0 to 20

comment:3 Changed 16 years ago by niki

  • Owner changed from Astea to niki
  • Status changed from new to s1a_analysis_started
  • Analysis_owners set to niki

taken

comment:4 Changed 16 years ago by niki

  • Status changed from s1a_analysis_started to s1b_analysis_finished

comment:5 Changed 16 years ago by boyan

  • Status changed from s1b_analysis_finished to new
  • Analysis_score changed from 0 to 2

The analysis of this tasks covers the requirements of BASE_PERSISTENCE_COMMONS_R0. This task is about the intermediate format that books will be stored in. You should clear that in the task requirements. Ask Milo for assistance on what goes in which of the two tasks.

comment:6 Changed 16 years ago by niki

  • Status changed from new to s1a_analysis_started

comment:7 Changed 16 years ago by niki

  • Status changed from s1a_analysis_started to s1b_analysis_finished

repair the task requirements

comment:8 Changed 16 years ago by peko

  • Status changed from s1b_analysis_finished to s1c_analysis_ok
  • Analysis_reviewers set to peko
  • Analysis_score changed from 2 to 3

Analysis is OK, may be some things can be more concrete. For example what are the related things to the Storage class, what are the things that should be moved etc. How is the BASE_PERSISTENCE_INTERMEDIATE_STORAGE connected with BASE_PERSISTENCE_COMMONS....

comment:9 Changed 16 years ago by boyan

  • Design_owners set to boyan
  • Owner changed from niki to boyan
  • Status changed from s1c_analysis_ok to s2a_design_started

taken for design along with BASE_PERSISTENCE_COMMONS_R0

comment:10 Changed 16 years ago by boyan

  • Status changed from s2a_design_started to s2b_design_finished

done in 1h (will compensate the extra effort on the BASE_PERSISTENCE_COMMONS_R0 task

comment:11 Changed 16 years ago by pav

  • Status changed from s2b_design_finished to s2c_design_ok
  • Design_score changed from 0 to 3.5
  • Design_reviewers set to pav

It is good(may be in the analysis had to be mentioned that this task depends on BASE_PERSISTENCE_COMMONS).It will be good if you provide class diagram with the methods(or at least these that will be refactored).

comment:12 Changed 16 years ago by boyan

  • Ticket_group set to GROUP_PERSISTENCE_R0

grouping tasks

comment:13 Changed 16 years ago by boyan

updating status of a grouped task

comment:14 Changed 16 years ago by boyan

  • Status changed from s2c_design_ok to s1c_analysis_ok

comment:15 Changed 16 years ago by deyan

  • Cc pav, deyan added

Batch update from file newimport.csv

comment:16 Changed 16 years ago by deyan

  • Cc pav, deyan removed

comment:17 Changed 15 years ago by deyan

  • Status changed from s1c_analysis_ok to closed
  • Resolution set to obsolete

Batch update from file query-obsoleted.csv

Note: See TracTickets for help on using tickets.