Ticket #20 (closed planned_task: obsolete)
PLATFORM_STANDARDS_GENERAL_R1
| Reported by: | Astea | Owned by: | todor |
|---|---|---|---|
| Priority: | 3 | Milestone: | M02b_PRE2b |
| Component: | SOPHIE_PLATFORM | Version: | 2.0 |
| Keywords: | Cc: | ||
| Category: | unknown | Effort: | 1 |
| Importance: | 80 | Ticket_group: | |
| Estimated Number of Hours: | Add Hours to Ticket: | ||
| Billable?: | Total Hours: | ||
| Analysis_owners: | tanya | Design_owners: | boyan, todor |
| Imp._owners: | Test_owners: | ||
| Analysis_reviewers: | pap | Changelog: | |
| Design_reviewers: | tanya | Imp._reviewers: | boyan |
| Test_reviewers: | Analysis_score: | 3 | |
| Design_score: | 3 | Imp._score: | 4 |
| Test_score: | 0 |
Description
wiki page: PLATFORM_STANDARDS_GENERAL_R1 - effort: 1d
Change History
comment:1 Changed 4 years ago by pap
- Owner changed from Astea to pap
- Status changed from new to analyzing
comment:4 Changed 4 years ago by todor
- Owner changed from pap to todor
- Status changed from analysis_accepted to designing
taken
comment:5 Changed 4 years ago by todor
- Status changed from designing to s1c_analysis_ok
design done in approximately 40m
comment:6 Changed 4 years ago by todor
- Status changed from s1c_analysis_ok to s2a_designing
adopting the new workflow
comment:7 Changed 4 years ago by todor
- Status changed from s2a_designing to s2b_designed
adopting the new workflow
comment:8 Changed 4 years ago by todor
it turned out that some thing needed to be added in the design section that is done now. the design took overall about 90m.
comment:9 Changed 4 years ago by deyan
- Status changed from s2b_designed to s2c_design_ok
3.5p You may add more than one analysis, design and implementation as examples.
comment:11 Changed 4 years ago by Tanya
- Status changed from s3a_implementing to s1c_analysis_ok
2p.
For coding tasks: It is not a good idea to link the result. A better idea is to link the change set of the commit where this modifications are done.
comment:12 Changed 4 years ago by boyan
- Owner changed from todor to boyan
- Status changed from s1c_analysis_ok to s2a_design_started
taken
comment:13 Changed 4 years ago by boyan
- Status changed from s2a_design_started to s2b_design_finished
comment:14 Changed 4 years ago by deyan
- Milestone changed from M02_PRE2 to M02b_PRE2b
Milestone change
comment:15 Changed 4 years ago by todor
- Status changed from s2b_design_finished to s2c_design_ok
3p by todor. The problem with coding tasks was fixed.
comment:16 Changed 4 years ago by todor
- Owner changed from boyan to todor
- Status changed from s2c_design_ok to s3a_implementation_started
taken
comment:17 Changed 4 years ago by todor
- Status changed from s3a_implementation_started to s3b_implementation_finished
PLATFORM_STANDARDS_GENERAL was thoroughly reviewed and improved:
- Links to PLATFORM_STANDARDS_ANALYSIS and PLATFORM_STANDARDS_DESIGN were added.
- Implementation section was improved and some minor errors were fixed.
Done in approximately 30m.
comment:18 Changed 4 years ago by boyan
- Design_owners set to boyan
- Design_score set to 3
- Imp._score set to 0
- Test_score set to 0
- Analysis_score set to 0
comment:19 Changed 4 years ago by boyan
- Status changed from s3b_implementation_finished to s3c_implementation_ok
- Imp._score changed from 0 to 4
- Imp._reviewers set to boyan
4 - the implementation is good enough and follows the design.
comment:20 Changed 3 years ago by deyan
Why do you reset the analysis score?
comment:23 Changed 3 years ago by Tanya
- Design_owners changed from boyan, Tanya to boyan
- Design_reviewers set to tanya
- Analysis_owners changed from Tanya to tanya
comment:25 Changed 3 years ago by pap
- Category set to unknown
- Analysis_reviewers set to pap
- Analysis_score changed from 0 to 3
setting custom fields
comment:26 Changed 3 years ago by deyan
- Status changed from s3c_implementation_ok to closed
- Resolution set to obsolete
Batch update from file query-obsoleted.csv