Version 4 (modified by todor, 16 years ago) (diff) |
---|
Analysis
Overview
The project blog shows the world what happens into Sophie 2 and how
Task requirements
Write two blog posts for this iteration
Post 1: (at the iteration start)
- Last sprint overview (added features and functionality)
- Explain interesting technologies introduced in this sprint
- What went well
- What could be better
- Decided improvements that will be applied
Post 2: (at the middle of the iteration)
- Progress overview
- Interesting technologies used
- Challanging tasks
- Applied improvements (from the sprint closing)
Task result
Two blog posts.
Implementation idea
Use the 0m03-closing.txt in the manage folder in the repository - there are collected the "What went well, what could be better and how to improve.
Related
SCS_PROJECT_BLOG_R0
SCS_PROJECT_BLOG_R1
SCS_PROJECT_BLOG_R2
How to demo
Show the blog posts.
Design
- File 0m03-closing.txt was created and stored in the reports directory of iteration 03:
Closing of Sprint 3 tasks complete/planned: 40/113 19 tasks were left as new: PRO_LIB_MODEL_COMMONS_R0 PRO_LIB_MODEL_PRO_OBJECTS_R0 PRO_LIB_MODEL_PRO_LISTS_R0 PRO_REGISTRY_PROP_VALUES_R0 PRO_REGISTRY_DEPENDENCY_TRACKING_R0 PRO_LIB_REMOTE_OBJECTS_R0 PRO_LIB_CONNECTION_INTERFACES_R0 PRO_LIB_LOCAL_CHANGE_SERVER_R0 CORE_LOCAL_STORAGE_R0 CORE_TEST_HELPERS_R0 CORE_ADDITIONS_R1 SCENE_COMMONS_R1 BASE_RESOURCE_LOCATOR_R0 BASE_SECURITY_MODEL_COMMONS_R0 PAGE_SCENE_IMPL_ALTERNATIVE_R0 TEXT_FRAME_NON_FLOW_R0 SEARCH_COMMONS_R0 MEDIA_ENGINE_IMPL_COMMON_R0 MEDIA_ENGINE_IMPL_ALTERNATIVE_R0 3 tasks were left in analysis started state: PRO_CHANGE_UNDO_MANAGER_R0 APP_PLUGIN_MANAGER_ABOUT_R0 MEDIA_ENGINE_IMPL_MAIN_R0 14 tasks were left in analysis finished state: UNPLANNED_DEVELOPMENT_OVERVIEW_R1 UNPLANNED_PLATFORM_STANDARDS_GENERAL_R0 PLATFORM_STANDARDS_CODE_R1 PLUGIN_SUPPORT_LIB_BASE_R1 PRO_LIB_CORE_PERFORMANCE_R0 PRO_CHANGE_INFOS_R0 PRO_CHANGE_MANAGER_R0 PRO_REGISTRY_PARENT_CHILD_R0 BASE_RESOURCE_POINTS_R0 DOCUMENT_FILE_MANAGEMENT_R0 BOOK_FILE_OPERATIONS_R0 EMBEDDED_BOOKS_RESOURCE_SUPPORT_R0 EMBEDDED_BOOKS_MANAGING_R0 GLOBAL_SPEC_MANAGING_R2 21 tasks were left in analysis ok state: PLATFORM_STRUCTURE_R2 PLATFORM_STANDARDS_DESIGN_R1 PLATFORM_STANDARDS_AUTO_TESTS_R1 PLATFORM_STANDARDS_MANUAL_TESTS_R1 PLATFORM_NFR_EXTENSIBILITY_R1 PLATFORM_DEPLOYMENT_BUILD_MAVEN_R1 PLATFORM_DEPLOYMENT_TARGET_APPLET_R0 PRO_LIB_CORE_THREAD_SAFETY_R0 PRO_CHANGE_COMMONS_R0 PRO_CHANGE_PRIMITIVES_R0 PRO_CHANGE_TRANSACTION_SAFETY_R0 PRO_CHANGE_COMPOSING_R0 BASE_MODEL_PAGE_ELEMENTS_R0 APP_BASIC_MENUS_R0 PAGE_TEMPLATE_BEHAVIOUR_R0 PAGE_TEMPLATES_LISTING_R0 PAGE_ELEMENT_ALIGNING_R0 PAGE_ELEMENT_MULTI_SELECT_R0 FRAME_HUD_R0 FRAME_Z_ORDER_R0 EMBEDDED_BOOKS_CONTENT_R0 7 tasks were left in design started state: PRO_LIB_CORE_MEMORY_MANAGEMENT_R0 BASE_MENUS_R0 APP_PLUGIN_STARTUP_R1 FRAME_TEMPLATES_R0 FRAME_PROPERTY_LOCKING_R0 SCS_ISSUE_TRACKER_MAINTENANCE_R2 SCS_TEST_TRACKING_MAINTENANCE_R2 2 tasks were left in design ok state: BASE_PERSISTENCE_INTERMEDIATE_STORAGE_R0 VIDEO_CONTENT_R0 2 tasks were left in implementation started state: PLUGIN_MODULE_STRUCTURE_R1 BASE_PERSISTENCE_COMMONS_R0 5 tasks were left in implementation finished state: PRO_LIB_CORE_MISUSE_DETECTION_R0 FRAME_MARGINS_R0 FRAME_PADDING_R0 AUDIO_CONTENT_R0 SCS_TEST_TRACKING_SETUP_R2 40 tasks were completed: PLATFORM_STANDARDS_REPOSITORY_R1 PLATFORM_DEPLOYMENT_BUILD_ECLIPSE_R1 PLATFORM_DEPLOYMENT_TARGET_JWS_R0 PLUGIN_DECOMPOSITION_R2 BASE_HALOS_R0 BASE_BOOK_COMMONS_R0 FRAME_INSETS_R0 FRAME_BOUNDS_R0 FRAME_BORDERS_R0 FRAME_POSITION_R0 FRAME_SIZE_R0 FRAME_CONTENT_R0 IMAGE_CONTENT_R0 S2S_WEB_COMMONS_R1 S2S_WEB_USER_RELATED_R0 S2S_WEB_BOOK_MANIPULATION_R0 S2S_WEB_BOOK_MANAGEMENT_R0 S2S_CORE_MOCK_SERVER_R0 S2S_WEB_SERVICES_R0 S2S_CORE_MODEL_R0 S2S_PERSIST_MODEL_R0 S2S_TESTING_SERVER_R0 SCS_SITE_DESIGN_R1 SCS_MACHINE_SETUP_R1 SCS_BACKUP_R2 SCS_INFORMATION_R1 SCS_REPO_MAINTENANCE_R2 SCS_WIKI_MAINTENANCE_R2 SCS_PROJECT_BLOG_R2 SCS_FORUM_R2 SCS_MAIL_LIST_R2 BUILD_SERVER_INSTANCE_R0 BUILD_SERVER_INTEGRATION_R0 BUILD_SERVER_REPORTS_R0 BUILD_SERVER_DEPLOYMENTS_R0 SCHEDULE_MAINTENANCE_R2 GLOBAL_SPEC_STRUCTURE_R1 INTERNAL_BACKLOG_STRUCTURE_R1 INTERNAL_BACKLOG_MAINTENANCE_R2 PROCESS_R2 What went well: * New PCs * Server team finished all their tasks * Team split * Progress checks are useful * Done more discussions * Utilize other rooms * New team members integrated * Some people with global vision What could be better: * Discipline and respecting the process * Availability of some remote team members * Need better organization * Small percentage of finished tasks * Better productivity needed How to improve summary: * Improve self discipline * Better organization between teams * Provide and discuss ideas about improval * Work towards the overall goal * Leads do daily reviews Total time spent for review and retrospection - 4 hours.
- Used the contents of the 0m03-closing.txt to create summary post for the last iteration:
Implementation
(Implementation results should be described and linked here (from the wiki or the repository))
Testing
Comments
(Write comments for this or later revisions here.)