| 6 | == Design == |
| 7 | The goal is to synchronize the effort allocations in sophie2-wbs.py to the resources.ods. |
| 8 | * Create new sheets |
| 9 | * Platform |
| 10 | * Core |
| 11 | * Base |
| 12 | * Main |
| 13 | * Extra |
| 14 | * SCS |
| 15 | * S2S |
| 16 | * Supporting |
| 17 | * End_Prod |
| 18 | * For each sheet do the following |
| 19 | * First row should be the same as in alloc sheet |
| 20 | * Second row should be the same as the corresponding row in alloc sheet (ex. for Platform sheet row 2 should be copied row 3 from alloc sheet) |
| 21 | * Third row - cells c3..p3 should contain "=X2-SUM(X4:X24) |
| 22 | When this table is ready, each task can be imported in this table. In row 3 can be seen easily how much days are remaining for this milestone for this group of tasks. |