    135135This task is going to be completed in 4 weekly tasks:  [[BR]] 
    136 '''1.''' Memory accesses implementation along with stable model with immutable operations, implementation of ModelChanges and all related functionality.  [[BR]] 
    137 '''2.''' File accesses implementation along with refactoring of the persistence logic.  [[BR]] 
    138 '''3.''' MetaChanges and undo/redo logic.  [[BR]] 
    139 '''4.''' Server accesses and logic for synchronization. [[BR]] 
     136'''0.''' This task - documentation and plan for all other related tasks. This should be done in the first week. 
     137'''1.''' Memory accesses implementation along with stable model with immutable operations, implementation of ModelChanges and all related functionality. This should be done by the end of the second week. [[BR]] 
     138'''2.''' File accesses implementation along with refactoring of the persistence logic. This should be done by the end of the third week.  [[BR]] 
     139'''3.''' MetaChanges and undo/redo logic. This should be done by the end of the fourth week.  [[BR]] 
     140'''4.''' Server accesses and logic for synchronization. This should be done by the end of the fifth week. [[BR]] 